• Hanna Region Transmission Development
  •  
  • Coyote Lake to Michichi Creek Transmission Project
  •  

Proposed Timelines

March - November 2010
Consultation with landowners and agencies


Fall 2010
Notification of preferred site and route options

November 2010
Submission of the facilities application to the Alberta Utilities Comission (AUC)

December 2011
If approval is granted by the AUC, construction will commence

September 2012
Facilities completed and operating

*Timing may be adjusted to reflect final plans.