July 2010
Consultation with landowners and agencies
July - August 2010
Review of preferred site and route options and submission of the facilities application to the Alberta Utilities Commission (AUC)
April 2011
If approval is granted by the AUC, construction will commence
December 2011
Facilities completed and operating
*Timing may be adjusted to reflect final plans.