• Hanna Region Transmission Development
  •  
  • Lanfine to Pemukan Transmission Project
  •  

Proposed Timelines 

March - November 2010
Consultation with landowners and agencies


October 2010
Notification of preferred site and route options

November 2010
Submission of the facilities application to the Alberta Utilities Comission (AUC)

December 2011
If approval is granted by the AUC, construction will commence

September2012
Facilities completed and operating

*Timing may be adjusted to reflect final plans.