• Hanna Region Transmission Development
  •  
  • Nevis to Stettler Transmission Project
  •  

Proposed Timelines

May - July 2010
Consultation with landowners and agencies

Fall  2010
Selection of preferred site and route options and submission of the facilities application to the Alberta Utilities Commission (AUC)

January 2011
If approval is granted by the AUC, construction will commence

September 2012
Facilities completed and operating

*Timing may be adjusted to reflect final plans.