Proposed Timelines
|
|
May - July 2010 Consultation with landowners and agencies
Fall 2010 Selection of preferred site and route options and submission of the facilities application to the Alberta Utilities Commission (AUC)
January 2011 If approval is granted by the AUC, construction will commence
September 2012 Facilities completed and operating
*Timing may be adjusted to reflect final plans.
|
|
|
|
|
|
|
|
|
|
|
|