March - November 2010
Consultation with landowners and agencies
October 2010
Notification of preferred site and route options
November 2010
Submission of the facilities application to the Alberta Utilities Comission (AUC)
December 2011
If approval is granted by the AUC, construction will commence
September 2012
Facilities completed and operating
*Timing may be adjusted to reflect final plans.