Proposed Timelines

March - July 2010
Consultation with landowners and agencies

July - August 2010
Selection of preferred site and route options and submission of the facilities application to the Alberta Utilities Commission (AUC)

January 2011
If approval is granted by the AUC, construction will commence

June 2012
Facilities completed and operating

*Timing may be adjusted to reflect final plans.